Looking to own a house in Zambia?
We facilitate the whole process.

We offer

Solid and proven, top quality housing project delivery. Several years of full-cycle real estate development in Zambia – land transaction, servicing, construction, title transfer, and rental property management.

The process

Interested parties will be contacted directly to get into detailed discussions.

CURRENT OPPORTUNITY – SILVER REST HOUSING PROJECT - 2022

Located in a fast-developing area of Lusaka, Silver Rest is our current offer.  

  • Located in vicinity of the University of Lusaka Silver Rest Campus
  • 8km east of Airport Roundabout
  • Amenities in the area (Garden City Mall, Waterfalls Mall, Mike Convention Centre, Lusaka Health Institute School of Nursing, Silver Rest Secondary School)
  • Gated community with perimeter wall fence
  • Tarred road to gate
  • Completed industrial borehole
  • 3-Phase electricity
  • 20 lots available

SOLUTION MADE BY THE DIASPORAS FOR THE DIASPORAS

This opportunity is ideal for individuals who are:

  • Challenged by the prospects of having to navigate a complex and lengthy land acquisition and building process
  • Looking at securing an investment asset for rental income (VRBO, Airbnb) or simply for use as a holiday home
  • Looking to ‘broaden’ their retirement options
  • Looking for a turnkey house in a secure location in Lusaka
  • Looking for an opportunity to invest in real estate in Lusaka
  • Not waiting for COVID to end before they can realize their dreams

This opportunity is also ideal for Real Estate Investment Groups (REIGs)

our ROADMAP

Release of Initial 20 Lots to purchasers. The first 20 lots are divided into Phases 1 to 4.

March - April 2022

Design & Permits for Phase 1

May - July 2022

Start of Phase 1 Construction

August 2022

Design & Permits for Phase 2

August - October 2022

Completion of Phase 1 Construction Start of Phase 2 Construction

November 2022

Design & Permits for Phase 3

November 2022 - January 2023

Completion of Phase 2 Construction Start of Phase 3 Construction

February 2023

Design & Permits for Phase 4

February - April 2023

Completion of Phase 3 Construction Start of Phase 4 Construction

May 2023

Completion of Phase 4 Construction

August 2023